Author: Dipl.-Ing. Christian M fchlh f6fer, Branch Manager, Swietelsky-Faber GmbH, Landsberg
In the listed Herrenm fchle in Aulendorf, Ravensburg district, the repair-needing pressure pipeline had to be urgently rehabilitated and as far as possible without interfering with the historic building fabric. The Landsberg branch of Swietelsky-Faber GmbH relied on a trenchless liner system from NordiTube and restored the water power supply to operation within just two days.
Hydropower with tradition
The Herrenm fchle in Aulendorf looks back on a centuries-old history: as early as 1606, the mill has been driven by hydropower. In 1949, an Ossberger cross-flow turbine was installed, which has since operated the mills via belt drive. On grinding days, master miller Mr. Vogel opens the sluice at the dam pond around 170 liters of water per second then set the turbine in motion.
Need for rehabilitation after 76 years of operation
After 76 years of continuous operation, however, increasing rehabilitation needs became apparent in the water supply line: according to the current TV inspection, the ageing steel pipe showed clear corrosion damage and cracks. In addition, with prolonged use, water seeped through the pipe bedding into the turbine house.
The Landsberg branch of Swietelsky-Faber GmbH responded immediately and was able to offer the mill operator an efficient solution: the trenchless rehabilitation of the line with a liner system from NordiTube Technologies SE.
Technically demanding framework conditions
The internal lining of the steel pipe posed particular requirements: the pipe route led over several 45 bends and ended directly in the turbine room a sensitive area with open access to flour production. To exclude any contamination, the entire work area in the turbine house was hermetically sealed off with foil.
Rehabilitation in just two days
After the removal of deposits and obstacles as well as a final condition assessment, the line was released for rehabilitation. In total, a section of approx. 110 meters with a diameter of 300 mm was rehabilitated.
The pressure-resistant liner was impregnated directly on site with epoxy resin using a mobile impregnation unit and then installed by steam curing. Installation took place via the existing water lock. After just two working days, the measure was completed the turbine could be reassembled and flour production resumed as planned.
Trenchless technology for special locations
The successful rehabilitation of the pressure line under demanding conditions shows how modern trenchless technologies can be used effectively and sustainably even in sensitive areas such as historic mills without major interventions in the building fabric and with minimal operational interruptions.
Special thanks go to the committed team at the Landsberg branch, which implemented the rehabilitation with a high level of professional expertise and great care. We also thank the client and the system manufacturer NordiTube for the trusting cooperation a successful project that once again shows how technical expertise and cooperative partnership lead to success.
More projects
-

Blomberg / Hamburg / Hamburg Head Office
-

Bodenheim: Close-fit method secures drinking water transport pipeline
Alzey / Hörsching
-

Gifhorn: Premiere in the railway environment of Deutsche Bahn
Blomberg
-

Staßfurt: Sustainable coating of a brine tank
Nuremberg
-

Oberaudorf: Concrete rehabilitation of the Röthenbach stream culvert
Freilassing
-

Tegernsee Brewery: Trenchless manhole rehabilitation with polyurea
Freilassing / Nuremberg
-

Power plant pipelines: Tailor-made solutions
Hörsching
-

Germering: Sustainable pipe rehabilitation reduces energy demand in wastewater treatment plants
Freilassing
-

Herrenmühle Aulendorf: Pressure pipeline sustainably rehabilitated
Hörsching / Landsberg
-

Altrip: Trenchless rehabilitation secures flood protection at the pumping station
Alzey
-

Wermelskirchen: Liner pipe technology shows strengths in combined rehabilitation
Alzey / Leipzig
-

Flensburg: Wound pipe technology in use beneath a former landfill
Hamburg / Leipzig
-

RHV Mittleres Rodltal: Mouth profile rehabilitated with UV pipe liner
Hörsching
-

Neuss: Sewer rehabilitation in large dimensions DN 1200–1500
Blomberg
-

Freyburg relies on SPR-EX wound pipe technology
Hamburg / Leipzig